At the 1st and 2nd production lines of the Amur GPP, pre-commissioning and commissioning work is underway.
Pre-commissioning and commissioning work continues at the 3rd line at the main gas separation unit.
The 4th line is undergoing leak tests, oil flushing, as well as installation of electric heating systems for pipelines. On the gas compressor units “Ladoga” No. 7 and No. 8, the lifting mechanism is being tested, as well as preparations for cold scrolling of the compressor.
On the 5th line, strength and density tests of the installed technological pipelines are carried out. Electrical work is underway at the substations of the ethane, NGL and nitrogen-helium mixture separation and helium fine purification and liquefaction units.
On the 6th technological line, the installation of the main metal structures is being carried out.